Text Box: 2006-2007 NGN Foundry Installation Schedule for MDFs
                                           
The dates below represent estimates when the Enterasys MDF E-7 will be replaced with Foundry routers in each building.  A date to replace the equipment will be mutually set by EITS Network Operations and building network support personnel.  If you do not see your building listed, it is probably on the list to be replaced in FY 08.  The replacement schedule FY 08 will be posted at a later date.  If you have question regarding this schedule, or if you need additional information, please contact the Network Operations Center at 2-3106.
 
     
Building Targeted Completion Date Status  
Tucker Hall 9/29/2006 Completed  
Animal/Dairy Science 10/11/2006 Completed  
Life Sciences 10/11/2006 Completed  
Morris 10/11/2006 Completed  
Boggs 10/11/2006 Completed  
Gilbert 10/11/2006 Completed  
Boyd 10/12/2006 Completed  
Plant Science 11/1/2006 Completed  
Aderhold 11/2/2006 Completed  
Snelling 11/3/2006 Completed  
Health Center 11/7/2006 Completed  
Poultry Science 11/8/2006 Completed  
Vet Med 11/9/2006 Completed  
Rivers Crossing 11/11/2006 Completed  
Bank of America 11/15/2006 Completed  
Academic Achievement 11/16/2006 Completed  
Academic 11/20/2006 Completed  
Chicopee 11/30/2006 Completed  
Family Housing H 12/6/2006 Completed  
Family Housing G 12/6/2006 Completed  
GGS 12/11/2006 Completed  
Bolton 12/11/2006 Completed  
Marine Science 12/11/2006 Completed  
Bioscience 12/11/2006 Completed  
Terrell Hall 12/11/2006 Completed  
Memorial Hall 1/15/2007 Completed  
Indoor Tennis 1/17/2007 Completed  
Tennis 1/17/2007 Completed  
Tennis Hall of Fame 1/17/2007 Completed  
PDRC 1/19/2007 Completed  
Dawson Hall 1/23/2007 Completed  
Ecology Annex 1/24/2007 Completed  
Pharmacy 1/25/2007 Completed  
Nichols Building 1/26/2007 Completed  
Hardman 1/30/2007 Completed  
Mary Lyndon 1/31/2007 Completed  
CAIS-Isotope Lab 1/31/2007 Completed  
Georgia Center 2/2/2007 Completed  
Printing 2/6/2007 Completed  
Family Housing Office 2/7/2007 Completed  
ECV--Rooker Hall 2/7/2007 Completed  
Soule 2/8/2007 Completed  
Boyd T-1 Switch 2/8/2007 Completed  
Food Science 2/8/2007 Completed  
Food Processing Lab 2/8/2007 Completed  
Art Museum 2/13/2007 Completed  
Four Towers 2/13/2007 Completed  
Performance Center 2/14/2007 Completed  
Environmental Health 2/15/2007 Completed  
ECV--McWhorter Hall 2/15/2007 Completed  
ECV--1514 2/15/2007 Completed  
ECV--1515 2/15/2007 Completed  
Journalism 2/16/2007 Completed  
McPhaul Center 2/20/2007 Completed  
Campus Planning 2/20/2007 Completed  
East Parking Deck 2/21/2007 Completed  
Ag Services 2/22/2007 Completed  
Science Library 2/27/2007 Completed  
ECV Commons 2/27/2007 Completed  
Barrow 3/1/2007 Completed  
Caldwell 3/13/2007 Completed  
Ramsey 3/15/2007 Completed  
Ecology 3/15/2007 Completed  
CAGT 3/16/2007 Completed  
Fine Arts 3/20/2007 Completed  
Old CCRC 3/27/2007 Completed  
Butts-Mehre 3/28/2007 Completed  
Coliseum 4/12/2007 Completed  
Central Food Storage 4/16/2007 Completed  
Baldwin Hall 5/8/2007 Completed  
Candler 5/9/2007 Completed  
Brumby 5/10/2007 Completed  
Milledge Hall 5/10/2007 Completed  
Auxiliary Services 5/10/2007 Completed  
New CCRC 5/15/2007 Completed  
Brooks Hall 5/17/2007 Completed  
TEC Services 5/23/2007 Completed  
Forestry 5/23/2007 Completed  
Main Library 6/3/2007 Completed  
Chemistry 6/3/2007 Completed  
CCQC 6/11/2007 Completed  
Riverbend North 6/14/2007 Completed  
Business Services 6/29/2007 Completed  
Administration Building 7/3/2007 Completed  
Text Box: 2007-2008 NGN Foundry Installation Schedule for MDFs
                                           
The dates below represent estimates when the Enterasys MDF E-7 will be replaced with Foundry routers in each building.  A date to replace the equipment will be mutually set by EITS Network Operations and building network support personnel.  If you do not see your building listed as part of the list above or below please contact the Network Operations Center at 2-3106.
 
 
 
 
 
 
 
 
 
 
Building Targeted Completion Date Status  
Bishop 8/1/2007    
Bookstore 8/1/2007    
Business Services Annex 8/6/2007    
Church Hall 8/6/2007    
Creswell 8/6/2007    
Denmark 8/13/2007    
Dean Rusk 8/13/2007    
Fanning 8/13/2007    
Franklin House 8/13/2007    
Foley Field 8/20/2007    
Georgia Center (uga comm.) 8/20/2007    
Garden Club 8/20/2007    
Hill Hall 8/27/2007    
Hoke Smith 8/27/2007    
Hoke Smith Annex 8/27/2007    
Human Resources 9/3/2007    
Instructional Plaza 9/3/2007    
Joe Brown 9/3/2007    
Law School 9/10/2007    
Leconte 9/10/2007    
Lipscomb 9/10/2007    
Lucy Cobb 9/17/2007    
Lumpkin 9/17/2007    
Lustrat 9/17/2007    
Meigs 9/24/2007    
Mell Hall 9/24/2007    
Military ROTC (Army) 9/24/2007    
Moore 10/1/2007    
Myers 10/1/2007    
New College 10/8/2007    
Old College 10/8/2007    
O-House 10/8/2007    
O-House Dining 10/15/2007    
Park Hall 10/15/2007    
Payne 10/15/2007    
Peabody 10/22/2007    
Phi Kappa 10/22/2007    
Physics 10/22/2007    
Public Safety (Hodgson Oil) 10/29/2007    
Psychology 10/29/2007    
Reed 10/29/2007    
Russell Hall 11/5/2007    
Rutherford 11/5/2007    
Saye 11/5/2007    
Slaughter 11/12/2007    
South Parking Deck 11/12/2007    
Student Learning Center 11/12/2007    
Stadium 11/12/2007    
Staff Training 11/19/2007    
Tate Center 11/19/2007    
Tanner 11/19/2007    
Thomas Street Art 11/26/2007    
Treanor 11/26/2007    
Visual Arts 11/26/2007    
Waddell 12/3/2007    
Wray Nicholson 12/3/2007    
Clark Howell 12/3/2007    
Music 12/10/2007    
Fred Building 12/10/2007    
Driftmier 12/10/2007    
Conner 12/10/2007